Al Khushaybi (KSB) 500 MW / 2,000 MWh battery energy storage IPP – EPC awarded to SEPCO
مشروع الخشيبي (KSB) لتخزين الطاقة بالبطاريات بقدرة 500 ميجاواط / 2000 ميجاواط ساعة – ترسية عقد الهندسة والتوريد والإنشاء على سيبكو
Electrical, substation, civil and BESS-container suppliers: SEPCO now procuring packages for a 2 GWh grid battery project.
| Type | Contract award |
|---|---|
| Status | Contract awarded – subcontracting open |
| Country | Saudi Arabia |
| Client / owner | Saudi Power Procurement Company (SPPC) / ENGIE – Haji Abdullah Alireza & Co. (developers) |
| Awarded to | Shandong Electric Power Construction Corp. (SEPCO) |
| Announced | 13 Oct 2026 |
| Project type | Power plants & renewables, Substations & transmission grids |
Trades and packages needed
- Solar PV & battery storage (main package)
- MV/HV substations & transmission lines (main package)
- Electrical installation (LV) (main package)
- Cables, switchgear & electrical materials (main package)
- Concrete works (in-situ)
- Earthworks, excavation & site grading
- Pre-engineered & modular buildings
- BMS, controls & SCADA
- Fire protection & fire alarm
What to do
The contract has been awarded. The winner will now buy materials and subcontract packages – contact their procurement team.