Bulk Drug Park 300 TPH steam plant + ~30 MW co-generation and steam distribution network – EPC + 25-yr O&M
ترسية عقد – India
Boiler, piping, insulation and E&I subcontractors should approach Steamhouse India on the 24-month steam and co-gen EPC at the Una Bulk Drug Park.
| Type | Contract award |
|---|---|
| Status | Contract awarded – subcontracting open |
| Country | India · Una, Himachal Pradesh |
| Client / owner | Himachal Pradesh Bulk Drug Park Infrastructure |
| Awarded to | Steamhouse India Ltd |
| Value | INR 3.11bn |
| Announced | 30 Sep 2026 |
| Project type | Power plants & renewables, Factories & industrial plants |
Trades and packages needed
- Mechanical erection & equipment installation (main package)
- Process piping fabrication & welding (main package)
- Pressure vessels, tanks & heat exchangers (main package)
- Industrial hot & cold insulation
- Electrical & instrumentation (E&I) installation
- Concrete works (in-situ)
- Structural steel fabrication & erection
- Facility management & O&M services
What to do
The contract has been awarded. The winner will now buy materials and subcontract packages – contact their procurement team.