Cheyenne Fuel Cell – 702 MW Bloom fuel-cell power plant for Google (20-yr PPA), ~USD 4bn, construction start 2026
ترسية عقد – United States
Multi-billion fuel-cell plant near Cheyenne moving to construction; civil, electrical/HV and gas-piping subcontractors should approach AEP and Bloom's installation partners now.
| Type | Contract award |
|---|---|
| Status | Contract awarded – subcontracting open |
| Country | United States · Cheyenne, WY |
| Client / owner | Cheyenne Fuel Cell (AEP 92% / Basalt Infrastructure Partners 8%) |
| Awarded to | Bloom Energy (fuel cells) |
| Value | USD 4bn |
| Announced | 14 Oct 2026 |
| Project type | Power plants & renewables, Data centres |
Trades and packages needed
- Concrete works (in-situ) (main package)
- Mechanical erection & equipment installation (main package)
- Electrical & instrumentation (E&I) installation (main package)
- MV/HV substations & transmission lines (main package)
- Earthworks, excavation & site grading
- Process piping fabrication & welding
- Cables, switchgear & electrical materials
- Equipment & crane rental
- Manpower supply
What to do
The contract has been awarded. The winner will now buy materials and subcontract packages – contact their procurement team.