Clean Energy Link – East Stage 1 – 92 km of 330 kV lines (Shotts–Cordering, Muja–Cordering), new Cordering terminal, Shotts & Muja terminal expansions
ترسية عقد – Australia
Tower steel, conductor, 330 kV switchgear and transformer suppliers, line-stringing and civil subcontractors should approach Acciona, GenusPlus and UGL for the CEL-East Stage 1 lines and terminals in WA's South West.
| Type | Contract award |
|---|---|
| Status | Contract awarded – subcontracting open |
| Country | Australia · Collie–Darkan, Western Australia |
| Client / owner | WA State Government / Western Power |
| Awarded to | Acciona, GenusPlus, UGL Engineering (UGL share ~AUD 478M) |
| Value | AUD 478M |
| Announced | 15 Oct 2026 |
| Project type | Substations & transmission grids |
Trades and packages needed
- MV/HV substations & transmission lines (main package)
- Cables, switchgear & electrical materials (main package)
- Structural steel fabrication & erection
- Earthworks, excavation & site grading
- Piling & deep foundations
- Concrete works (in-situ)
- Electrical & instrumentation (E&I) installation
- Steel, rebar & structural sections supply
- Heavy lifting, rigging & transport
- Equipment & crane rental
What to do
The contract has been awarded. The winner will now buy materials and subcontract packages – contact their procurement team.