CTA Blue Line Forest Park Branch Rebuild Phase 2 – Kedzie–Pulaski track reconstruction (~8,000 ft slow zones incl. Pulaski Crossover), traction power, signals & communications upgrades
ترسية عقد – United States
Rail, ballast and tie suppliers, traction-power and signalling subcontractors should approach Kiewit on CTA's USD 86.3M Blue Line track rebuild starting summer 2027.
| Type | Contract award |
|---|---|
| Status | Contract awarded – subcontracting open |
| Country | United States · Chicago, Illinois |
| Client / owner | Chicago Transit Authority (CTA) |
| Awarded to | Kiewit Infrastructure Company |
| Value | USD 86.3M |
| Announced | 18 Nov 2026 |
| Project type | Rail & metro |
Trades and packages needed
- Railway track & systems installation (main package)
- Earthworks, excavation & site grading
- Storm-water drainage & culverts
- MV/HV substations & transmission lines
- BMS, controls & SCADA
- ELV, ICT & security systems (CCTV, access, cabling)
- Cables, switchgear & electrical materials
- Steel, rebar & structural sections supply
- Equipment & crane rental
- Site security & traffic management
What to do
The contract has been awarded. The winner will now buy materials and subcontract packages – contact their procurement team.