Ecuador–Peru 500 kV interconnection (Ecuador side) – Chorrillos–Pasaje 207 km and Pasaje–Frontera 78 km double-circuit lines, Pasaje 500/230 kV 600 MVA substation, Chorrillos bay & reactors; EPC contract awarded
ترسية عقد – Ecuador
Tower steel, conductor/OPGW, HV substation equipment and line-construction subcontractors should identify the winner of CELEC's 500 kV Ecuador–Peru link (winner not named in report).
| Type | Contract award |
|---|---|
| Status | Contract awarded – subcontracting open |
| Country | Ecuador · Guayas / El Oro |
| Client / owner | CELEC EP – Transelectric |
| Announced | 17 Nov 2026 |
| Project type | Substations & transmission grids |
Trades and packages needed
- MV/HV substations & transmission lines (main package)
- Structural steel fabrication & erection (main package)
- Cables, switchgear & electrical materials (main package)
- Electrical & instrumentation (E&I) installation (main package)
- Concrete works (in-situ)
- Earthworks, excavation & site grading
- Piling & deep foundations
- Heavy lifting, rigging & transport
- Equipment & crane rental
- Camps, temporary facilities & catering
- Land surveying & geotechnical investigation
What to do