HUMAIN / center3 Riyadh data centre phase 1 (16.2 MW IT, 50 MW total) – civil, architectural, MEP & infrastructure works, 16 months
مركز بيانات هيوماين وسنتر3 في الرياض – المرحلة الأولى (16.2 ميغاواط) – أعمال مدنية ومعمارية وكهروميكانيكية وبنية تحتية
JV now buys cooling, power (UPS/generators), fire protection and ELV packages for a fast-track 16-month Riyadh data centre build.
| Type | Contract award |
|---|---|
| Status | Contract awarded – subcontracting open |
| Country | Saudi Arabia · Riyadh |
| Client / owner | HUMAIN / center3 (stc Group) |
| Awarded to | Hassan Allam Construction / Sterling & Wilson JV |
| Value | SAR 750M (~USD 200M) |
| Announced | 06 Oct 2026 |
| Project type | Data centres |
Trades and packages needed
- HVAC & ventilation (main package)
- Electrical installation (LV) (main package)
- Generators, UPS & standby power (main package)
- District cooling & chilled-water plants
- Fire protection & fire alarm
- ELV, ICT & security systems (CCTV, access, cabling)
- BMS, controls & SCADA
- Concrete works (in-situ)
- Structural steel fabrication & erection
- Cables, switchgear & electrical materials
What to do
The contract has been awarded. The winner will now buy materials and subcontract packages – contact their procurement team.