Lot 1 – main water pipeline PK0+00–PK164+05 and pump station, Zones 2F/2G/3K, Dusti District (World Bank)
ترسية عقد – Tajikistan
18-month water main and pumping station award; pipe, valve and pump suppliers and earthworks subcontractors should approach the BALH–Sichuan Tianhong JV.
| Type | Contract award |
|---|---|
| Status | Contract awarded – subcontracting open |
| Country | Tajikistan · Dusti District |
| Client / owner | Tajikistan Water Supply and Sanitation Investment Project |
| Awarded to | LLC BALH / Sichuan Tianhong Construction |
| Value | TJS 39.9M |
| Announced | 01 Oct 2026 |
| Project type | Pipelines & utility networks, Water, desalination & treatment |
Trades and packages needed
- Water, sewer & utility networks (incl. HDD) (main package)
- Pipes, valves & fittings supply (main package)
- HVAC, pumps & mechanical equipment supply (main package)
- Earthworks, excavation & site grading
- Concrete works (in-situ)
- Electrical installation (LV)
What to do
The contract has been awarded. The winner will now buy materials and subcontract packages – contact their procurement team.