Origem Energia 371 MW gas-engine flexible capacity plants (Pilar Nova, Pilar, Manguaba I–V) – process EPC
ترسية عقد – Brazil
Mechanical, piping and E&I subcontractors can approach Wärtsilä on the 371 MW Origem Energia gas plants EPC in Brazil.
| Type | Contract award |
|---|---|
| Status | Contract awarded – subcontracting open |
| Country | Brazil |
| Client / owner | Origem Energia |
| Awarded to | Wärtsilä |
| Announced | 20 Oct 2026 |
| Project type | Power plants & renewables |
Trades and packages needed
- Mechanical erection & equipment installation (main package)
- Process piping fabrication & welding (main package)
- Electrical & instrumentation (E&I) installation (main package)
- MV/HV substations & transmission lines
- Concrete works (in-situ)
- Structural steel fabrication & erection
- Heavy lifting, rigging & transport
- Cables, switchgear & electrical materials
What to do
The contract has been awarded. The winner will now buy materials and subcontract packages – contact their procurement team.