PDO Al-Ghubar sour gas-oil gravity drainage (GOGD) facility, Block 6 – EPC incl. separators, gas-lift compressor, 132 kV substation, pipeline network and two remote manifold stations
منشأة الصرف الجاذبي للغاز والنفط الحامض في حقل الغبار، الامتياز 6 – أعمال الهندسة والتوريد والإنشاء شاملة الفواصل وضاغط رفع الغاز ومحطة 132 ك.ف وشبكة الأنابيب ومحطتي تجميع
Sour-service valve, piping, NDT, E&I and coating subcontractors should approach Jereh for packages on this PDO Block 6 EPC facility.
| Type | Contract award |
|---|---|
| Status | Contract awarded – subcontracting open |
| Country | Oman · Qarn Alam |
| Client / owner | Petroleum Development Oman (PDO) |
| Awarded to | Jereh Group |
| Announced | 12 Nov 2026 |
| Project type | Oil, gas & petrochemical plants, Pipelines & utility networks |
Trades and packages needed
- Process piping fabrication & welding (main package)
- Mechanical erection & equipment installation (main package)
- Pressure vessels, tanks & heat exchangers (main package)
- Pipeline construction (main package)
- Electrical & instrumentation (E&I) installation (main package)
- MV/HV substations & transmission lines
- NDT, inspection & certification
- Cathodic protection
- Industrial blasting, coating & painting
- Scaffolding & access
- Concrete works (in-situ)
- Pipes, valves & fittings supply
What to do
The contract has been awarded. The winner will now buy materials and subcontract packages – contact their procurement team.