Phantom Warrior Microgrid, Fort Hood – ~3 MW gas reciprocating generation, 1.5 MW solar parking canopy, 1 MW BESS, automated switching (14-day islanding), completion May 2029
ترسية عقد – United States
Gas genset, solar canopy, battery storage, switchgear and controls suppliers and electrical subcontractors should approach Dominion Privatization Texas for this Army microgrid build.
| Type | Contract award |
|---|---|
| Status | Contract awarded – subcontracting open |
| Country | United States · Fort Hood, Texas |
| Client / owner | U.S. Army Corps of Engineers (for U.S. Army Fort Hood) |
| Awarded to | Dominion Privatization Texas (Dominion Energy subsidiary) |
| Value | USD 61.5M |
| Announced | 02 Nov 2026 |
| Project type | Defense & security facilities, Power plants & renewables |
Trades and packages needed
- Generators, UPS & standby power (main package)
- Solar PV & battery storage (main package)
- MV/HV substations & transmission lines
- Electrical installation (LV)
- BMS, controls & SCADA
- Cables, switchgear & electrical materials
- Electrical & instrumentation (E&I) installation
What to do
The contract has been awarded. The winner will now buy materials and subcontract packages – contact their procurement team.