Querétaro–Saltillo passenger train Tramo 1, Querétaro–San Miguel de Allende 68 km – design & construction of viaducts, tunnels, stations and crossings
ترسية عقد – Mexico
Mota-Engil won the MXN 22.4bn design-build of the 68 km Querétaro–San Miguel de Allende section (works from 17 Oct 2026, 973 days); viaduct, precast, tunnelling, track and equipment-rental subcontractors should approach the consortium now.
| Type | Contract award |
|---|---|
| Status | Contract awarded – subcontracting open |
| Country | Mexico · Querétaro – San Miguel de Allende |
| Client / owner | Agencia de Trenes y Transporte Público Integrado (ATTRAPI) |
| Awarded to | Mota-Engil México / Mota-Engil Engenharia e Construção / Mota-Engil Engenharia Construção África consortium |
| Value | MXN 22.4bn |
| Announced | 05 Oct 2026 |
| Project type | Rail & metro, Bridges & tunnels |
Trades and packages needed
- Bridge & flyover construction (main package)
- Tunnelling & microtunnelling (main package)
- Railway track & systems installation (main package)
- Precast & prestressed concrete (main package)
- Earthworks, excavation & site grading (main package)
- Concrete works (in-situ) (main package)
- Piling & deep foundations
- Rebar cutting, bending & fixing
- Formwork & falsework
- Structural & civil design
- Ready-mix concrete, cement & aggregates
- Steel, rebar & structural sections supply
- Equipment & crane rental
What to do
The contract has been awarded. The winner will now buy materials and subcontract packages – contact their procurement team.