Savannah River Plutonium Processing Facility – conversion of unfinished ~400,000 sq ft MOX building into main pit-production process building (50 pits/yr), ~160-acre support facilities; full construction authorised
ترسية عقد – United States
Nuclear-qualified mechanical, process piping, HVAC/filtration, E&I and glovebox fabricators should register with SRNS (Fluor–HII) now that the USD 23.5bn baseline allows full construction.
| Type | Contract award |
|---|---|
| Status | Contract awarded – subcontracting open |
| Country | United States · Aiken, SC |
| Client / owner | US Department of Energy / NNSA |
| Awarded to | Savannah River Nuclear Solutions (Fluor–HII); design: Fluor Federal Services, Merrick & Co. (gloveboxes) |
| Value | USD 23.5bn |
| Announced | 09 Nov 2026 |
| Project type | Factories & industrial plants, Defense & security facilities |
Trades and packages needed
- Mechanical erection & equipment installation (main package)
- Process piping fabrication & welding (main package)
- Electrical & instrumentation (E&I) installation (main package)
- HVAC & ventilation (main package)
- Structural steel fabrication & erection
- Concrete works (in-situ)
- Fire protection & fire alarm
- BMS, controls & SCADA
- NDT, inspection & certification
- Pressure vessels, tanks & heat exchangers
- Heavy lifting, rigging & transport
- Manpower supply
What to do
The contract has been awarded. The winner will now buy materials and subcontract packages – contact their procurement team.