SBEE distribution network densification works Phase 2 – BJ-PIU-388868-CW-RFB, 18 months (World Bank BEAS project)
ترسية عقد – Benin
MV/LV cable, pole, pole-mounted transformer and meter suppliers and line-construction subcontractors should target TBEA and ENIM–XEE on these World Bank-funded SBEE grid densification contracts (~EUR 20M combined).
| Type | Contract award |
|---|---|
| Status | Contract awarded – subcontracting open |
| Country | Benin · Atlantique, Mono, Ouémé & Plateau departments |
| Client / owner | Benin Electricity Access Scale-up (BEAS) project (P173749) – Société Béninoise d'Energie Electrique (SBEE) |
| Awarded to | TBEA Co. Ltd (Ouémé/Plateau; XOF 2.22bn + EUR 8.68M); ENIM–XEE (Atlantique/Mono; XOF 5.23bn) |
| Value | XOF 7.45bn + EUR 8.68M |
| Announced | 05 Nov 2026 |
| Project type | Substations & transmission grids |
Trades and packages needed
- Cables, switchgear & electrical materials (main package)
- MV/HV substations & transmission lines (main package)
- Electrical installation (LV)
What to do
The contract has been awarded. The winner will now buy materials and subcontract packages – contact their procurement team.