Shadwan (Scatec, 900 MW, ~USD 1bn) and Shokeir (Engie/Toyota Tsusho/Orascom, 900 MW) wind farms – cabinet golden licences granted
مشروعا رياح شدوان (سكاتك، 900 ميجاوات، نحو مليار دولار) والشقير (إنجي/تويوتا تسوشو/أوراسكوم، 900 ميجاوات) – منح الرخصة الذهبية من مجلس الوزراء
Wind-turbine foundation contractors, crane/heavy-haul firms and HV substation suppliers can approach Scatec and the Engie–Toyota–Orascom consortium now that both 900 MW Gulf of Suez wind farms hold golden licences.
| Type | Pre-qualification / EOI |
|---|---|
| Status | Open – deadline not published |
| Country | Egypt · Ras Shokeir / Gulf of Suez (Red Sea) |
| Client / owner | Egyptian Electricity Transmission Company (offtaker) |
| Parties | Scatec (Shadwan); Engie / Aeolus–Toyota Tsusho / Orascom Construction (Shokeir Wind Energy) |
| Value | USD 1bn |
| Announced | 29 Oct 2026 |
| Project type | Power plants & renewables, Substations & transmission grids |
Trades and packages needed
- Heavy lifting, rigging & transport (main package)
- Concrete works (in-situ) (main package)
- MV/HV substations & transmission lines (main package)
- Cables, switchgear & electrical materials (main package)
- Earthworks, excavation & site grading
- Roads, asphalt paving & road marking
- Equipment & crane rental
- Construction logistics, freight & customs
What to do
Early stage – get on the client's or bidders' vendor lists now.