Sishen–Saldanha iron ore export railway (861 km) rehabilitation programme to 2030 – track renewal, electrical and signalling upgrades, rolling stock repairs
تأهيل مسبق – South Africa
R8.9bn multi-year heavy-haul rail rehabilitation just launched; track, signalling and traction-power contractors should track upcoming Transnet packages.
| Type | Pre-qualification / EOI |
|---|---|
| Status | Open – deadline not published |
| Country | South Africa · Northern Cape / Western Cape |
| Client / owner | Government of South Africa (Department of Transport); line operated by Transnet Freight Rail |
| Value | USD 541M |
| Announced | 16 Oct 2026 |
| Project type | Rail & metro |
Trades and packages needed
- Railway track & systems installation (main package)
- MV/HV substations & transmission lines
- ELV, ICT & security systems (CCTV, access, cabling)
- BMS, controls & SCADA
- Equipment & crane rental
- Steel, rebar & structural sections supply
What to do
Early stage – get on the client's or bidders' vendor lists now.