SWA strategic water storage – seven reservoirs (730,000 m³) and 32 km of transmission pipelines, plus Al Uyaynah and Al Jubaylah water projects – under construction, completion 2027
مشروع التخزين الاستراتيجي للمياه التابع لهيئة المياه السعودية – سبعة خزانات (730 ألف م³) و32 كم من خطوط النقل، إضافة إلى مشروعي مياه العيينة والجبيلة – قيد الإنشاء والإنجاز في 2027
SWA's SAR 508M reservoir and pipeline programme north of Riyadh is in construction for 2027 completion; valve, pump, SCADA and waterproofing suppliers should contact the site contractors.
| Type | Contract award |
|---|---|
| Status | Contract awarded – subcontracting open |
| Country | Saudi Arabia · Riyadh region (Al-Ghat, Al Majmaah, Shaqra, Ghanman) |
| Client / owner | Saudi Water Authority (SWA) |
| Value | SAR 508M |
| Announced | 17 Nov 2026 |
| Project type | Water, desalination & treatment, Pipelines & utility networks |
Trades and packages needed
- Concrete works (in-situ) (main package)
- Pipeline construction (main package)
- Pipes, valves & fittings supply (main package)
- Waterproofing
- Water, sewer & utility networks (incl. HDD)
- HVAC, pumps & mechanical equipment supply
- Electrical & instrumentation (E&I) installation
- BMS, controls & SCADA
What to do
The contract has been awarded. The winner will now buy materials and subcontract packages – contact their procurement team.