Three BESS projects, 1,500 MW / 6,000 MWh – storage services agreements, SAR 3.25bn
ثلاثة مشاريع لتخزين الطاقة بالبطاريات بقدرة 1500 ميجاواط / 6000 ميجاواط ساعة – مكة المكرمة وحائل
Grid batteries incl. a 380 kV substation extension – civil, HV and commissioning subcontractors.
| Type | Contract award |
|---|---|
| Status | Contract awarded – subcontracting open |
| Country | Saudi Arabia · Al-Muwaih, Haden & Kahafah |
| Client / owner | Saudi Power Procurement Company (SPPC) |
| Awarded to | Saudi Energy Company (developer) |
| Value | SAR 3.25bn (USD 867M) |
| Announced | 30 Sep 2026 |
| Project type | Substations & transmission grids, Power plants & renewables |
Trades and packages needed
- Solar PV & battery storage (main package)
- MV/HV substations & transmission lines (main package)
- Cables, switchgear & electrical materials
- Earthworks, excavation & site grading
- Concrete works (in-situ)
- Electrical installation (LV)
What to do
The contract has been awarded. The winner will now buy materials and subcontract packages – contact their procurement team.