Three CCGT power plants (2,800–3,000 MW) – technical consultant appointed for concept design, site selection and EPC tender documents
ثلاث محطات كهرباء بالدورة المركبة (2,800–3,000 ميجاواط) – تعيين استشاري فني للتصميم المبدئي واختيار المواقع ووثائق مناقصة الهندسة والتوريد والإنشاء
Oman is preparing 2.8–3 GW of new gas-fired capacity; Energoprojekt ENTEL will write the EPC tender documents – EPC contractors, OEMs and site-survey firms should position early.
| Type | Pre-qualification / EOI |
|---|---|
| Status | Open – deadline not published |
| Country | Oman |
| Client / owner | Nama Power and Water Procurement (PWP) |
| Announced | 29 Sep 2026 |
| Project type | Power plants & renewables, Substations & transmission grids |
Trades and packages needed
- MEP & process design engineering (main package)
- Mechanical erection & equipment installation (main package)
- MV/HV substations & transmission lines (main package)
- Land surveying & geotechnical investigation
- Process piping fabrication & welding
- Electrical & instrumentation (E&I) installation
- Concrete works (in-situ)
- Heavy lifting, rigging & transport
- Project management & construction supervision
What to do
Early stage – get on the client's or bidders' vendor lists now.