Waroona Renewable Energy Project Stage One – 132 MW solar + 81.5 MW/562 MWh BESS: AUD 280M debt signed, fixed-price EPC to Monford Group, BESS by Trina Storage
ترسية عقد – Australia
Electrical, piling and civil subcontractors and labour hire firms in WA should approach Monford Group as Waroona Stage One heads to financial close and construction.
| Type | Contract award |
|---|---|
| Status | Contract awarded – subcontracting open |
| Country | Australia · Waroona (south of Perth), WA |
| Client / owner | Frontier Energy (WRP Finance) |
| Awarded to | Monford Group (EPC); Trina Storage (BESS) |
| Value | AUD 280M (~USD 196M) |
| Announced | 03 Nov 2026 |
| Project type | Power plants & renewables |
Trades and packages needed
- Solar PV & battery storage (main package)
- MV/HV substations & transmission lines
- Mechanical erection & equipment installation
- Electrical & instrumentation (E&I) installation
- Cables, switchgear & electrical materials
- Earthworks, excavation & site grading
- Piling & deep foundations
- Construction logistics, freight & customs
What to do
The contract has been awarded. The winner will now buy materials and subcontract packages – contact their procurement team.