Badain Jaran energy base coal-power railway spur (4.85 km) – EPC first-ranked candidate
ترسية عقد – China
Track, earthworks and drainage subcontractors can approach the winning EPC for the 12-month rail spur linking a 4 GW coal plant to the Jiuquan–Ejina line.
| Type | Contract award |
|---|---|
| Status | Contract awarded – subcontracting open |
| Country | China · Jiuquan |
| Client / owner | Badain Jaran energy base 4x1,000 MW coal power project (owner not named) |
| Awarded to | China Railway Eryuan Engineering Group (first-ranked candidate) |
| Value | CNY 117.07M |
| Announced | 16 Oct 2026 |
| Project type | Rail & metro, Power plants & renewables |
Trades and packages needed
- Earthworks, excavation & site grading (main package)
- Railway track & systems installation (main package)
- Storm-water drainage & culverts
- Concrete works (in-situ)
- Land surveying & geotechnical investigation
What to do
The contract has been awarded. The winner will now buy materials and subcontract packages – contact their procurement team.