Ethane & propane trunk pipelines in a single corridor, Tengiz–Karabatan SEZ (~210 km each) – construction started
ترسية عقد – Kazakhstan
Line-pipe, valve, leak-detection, NDT and camp/equipment suppliers can approach the CPPE-led consortium building KMG PetroChem's Atyrau ethane and propane pipelines.
| Type | Contract award |
|---|---|
| Status | Contract awarded – subcontracting open |
| Country | Kazakhstan · Atyrau region |
| Client / owner | KMG PetroChem LLP (KazMunayGas) |
| Awarded to | CPPE (Kazakhstan) LLP / China Petroleum Pipeline Engineering-led consortium incl. CITIC Construction |
| Announced | 22 Oct 2026 |
| Project type | Pipelines & utility networks, Oil, gas & petrochemical plants |
Trades and packages needed
- Pipeline construction (main package)
- Pipes, valves & fittings supply (main package)
- NDT, inspection & certification (main package)
- Cathodic protection
- Earthworks, excavation & site grading
- Electrical & instrumentation (E&I) installation
- BMS, controls & SCADA
- Camps, temporary facilities & catering
- Equipment & crane rental
What to do
The contract has been awarded. The winner will now buy materials and subcontract packages – contact their procurement team.