LanWin2 'LanWin beta' 2 GW offshore HVDC converter platform – fabrication of steel foundation (jacket) awarded by Dragados Offshore to Smulders (Eiffage Métal)
ترسية عقد – Germany
Jacket fabrication split between Belgium and Poland with assembly in the Netherlands, works from early 2027 to 2030; plate/tubular steel suppliers, blasting/coating and NDT firms should contact Smulders.
| Type | Contract award |
|---|---|
| Status | Contract awarded – subcontracting open |
| Country | Germany · German North Sea |
| Client / owner | Dragados Offshore (for TenneT Germany LanWin2) |
| Awarded to | Smulders (Eiffage Métal) |
| Announced | 16 Nov 2026 |
| Project type | Substations & transmission grids, Offshore platforms & marine O&G |
Trades and packages needed
- Structural steel fabrication & erection (main package)
- Offshore & modular fabrication yards (main package)
- Steel, rebar & structural sections supply (main package)
- Industrial blasting, coating & painting
- NDT, inspection & certification
- Heavy lifting, rigging & transport
- Construction logistics, freight & customs
What to do
The contract has been awarded. The winner will now buy materials and subcontract packages – contact their procurement team.