1614 live leads · 54 new today · updated 22 Oct 2026Contactمناقصات يومية مجانية
Tender Leads DailyConstruction tenders & awards · every morning

Today › United States

Open tender

El Centro Generating Station Unit 4 Repowering – EPC services RFP (six RICE generators, 113 MW fast-start, replacing 1968 boiler/steam turbine)

مناقصة – United States

Power-plant EPC contractors and engine-generator suppliers should bid the IID Unit 4 repowering before 25 Nov 2026; project budget about USD 235M with COD targeted mid-2028.

TypeOpen tender
StatusOpen – closes 25 Nov 2026 (34 days)
CountryUnited States · El Centro, CA
Client / ownerImperial Irrigation District (IID)
ValueUSD 235M
Announced14 Oct 2026
Deadline25 Nov 2026
Project typePower plants & renewables

Trades and packages needed

What to do

Register with the client and request the tender documents before the deadline.

Read the official source → Report a correction

Related live opportunities

Pre-qualification / EOICanadaCAD 479MOpen – deadline not published

Hitachi Energy transformer insulation (pressboard & laminates) factory – new 21,000 m² plant, Canada's first pressboard line, completion by 2028 (CAD 479M)

Client: Hitachi Energy

Contract awardIndiaINR 23.49bnContract awarded – subcontracting open

Kalpataru Projects International – new EPC orders in power T&D and buildings & factories (INR 2,349 crore)

Awarded to Kalpataru Projects International Ltd (KPIL) · Client: Undisclosed (India)

Pre-qualification / EOIMozambiqueUSD 130MOpen – closes 31 Oct 2026 (9 days)

Temane 75 MW gas-fired power plant (reciprocating engines) – EPC tender launched, applications by 31 Oct (USD 130M)

Client: Eni Rovuma Basin B.V. Mozambique (with EDM)

Contract awardIraq · العراقContract awarded – subcontracting open

Ratawi field upstream works, Gas Growth Integrated Project (USD 27bn programme) – Enka mobilises workforce on site

Awarded to Enka · Client: Gas Growth Integrated Project (GGIP), Iraq

Pre-qualification / EOIUAE · الإماراتOpen – deadline not published

Umm Shaif Long-Term Development Plan 2.1 – two offshore EPC packages: EOI completed, early contractor engagement

Client: ADNOC Offshore

Want more leads like this?Get Mechanical erection & equipment installation, Electrical & instrumentation (E&I) installation opportunities in your inbox every morning.
Get free alerts →